| 9/20/2005 | Bridge Blast Fund Raiser |
| 9/8/2005 | Wingo Way on-ramp is Complete |
| 9/1/2005 | Bridge Update on SCETV |
| 6/9/2005 | Bridge Opens July 16th, 2005 |
| 5/2/2005 | Opening Date Soon to Be Set |
| 4/13/2005 | The Grace Bridge ramp onto I-26W is closed |
| 3/31/2005 | New Meeting Street Ramp onto I-26 W |
| 3/11/2005 | The mid-span gap is closed |
| 2/19/2005 | Girders completed |
| 2/11/2005 | The last cables have been placed |
| 12/14/2004 | Both Side Span Connections Are Now Completed |
| 12/3/2004 | New Signage Goes Up on Bridge |
| 11/20/2004 | All columns and pier caps are now in place |
| 11/11/2004 | The Western Side Span Is Connected |
| 11/8/2004 | New Decorative Lighting on Meeting Street |
| 10/22/2004 | SCETV Provides Bridge Updates |
| 10/22/2004 | Extreme Engineering |
| 8/24/2004 | 64 of 128 cables in place |
| 8/4/2004 | Girders in Mount Pleasant |
| 6/21/2004 | Welcome to Extreme Engineering |
| 6/7/2004 | 1st Bridge Deck in Mount Pleasant |
| 5/24/2004 | 425 drilled shafts are complete |
| 5/24/2004 | Both towers are "topped out" |
| 5/20/2004 | Romney Street exit is now open |
| 5/18/2004 | Western tower is completed |
| 4/6/2004 | New Construction Camera Now Online |
| 3/15/2004 | Construction Update on SCETV |
| 11/14/2003 | I-Beam Girders on Pearman Pier Cap |
| 11/14/2003 | Safety net on western tower |
| 11/14/2003 | Construction begins on Morrison Drive on-ramp |
| 9/30/2003 | Girders To Be Placed Across Existing Bridges |
| 9/24/2003 | First of 2 Box Girders to Be Placed Over I-26 |
| 8/27/2003 | Tower Cranes on the Rise |
| 8/25/2003 | Column Rises to a Broader Top |
| 8/22/2003 | 50% of the On-site Concrete Has Been Placed |
| 6/18/2003 | 1st Concrete Girders To Be Placed |
| 6/11/2003 | The first steel girders are put into place |
| 6/2/2003 | Falswork in place for Western Tower Crossbeam |
| 5/5/2003 | SCETV Documentary on Fri., June 13th |
| 5/1/2003 | Post Tensioning Cable |
| 4/15/2003 | 70% of Drilled Shafts are in the ground |
| 2/6/2003 | 20000th longitudinal rebar weld |
| 10/10/2002 | Work Begins on Meeting Street |
| 10/6/2002 | Getting Ready for Tower Pier Footings |
| 10/1/2002 | Activity Heats Up in Mt. Pleasant |
| 9/25/2002 | 1st Shipload of Armor Stone Arrives This Week |
| 9/20/2002 | Columns Rising from the Drilled Shafts |
| 9/19/2002 | First Large Pier Cap Can Be Seen |
| 9/3/2002 | The 8th limestone shipload for the east tower |
| 9/3/2002 | Defining the alignment of the Project. |
| 8/15/2002 | The first pier cap form for the Project. |
| 8/1/2002 | Western tower shafts and base are in place. |
| 7/26/2002 | The drilled shafts create a steady anchor. |
| 7/17/2002 | Crews work to set the 400 drilled shafts. |
| 7/12/2002 | Mount Pleasant construction access road. |
| 7/12/2002 | Project management for maximimum efficiency. |
| 7/3/2002 | An important anniversary for the project. |
| 6/25/2002 | The first shiploads of quarry stone arrive. |
| 6/17/2002 | Eleven western tower shafts have been set. |
| 6/10/2002 | Construction has effects on boat traffic. |
| 6/10/2002 | Project Partnering with SCDOT |
| 5/15/2002 | Moving the Drum Island Dike. |
| 4/29/2002 | Lee St. lots have been filled in with houses. |
| 4/29/2002 | PBC has begun to pour concrete. |